Month-End Stock Fits. Tuesday’s Delivery Does Not
Core’s weekly stock plan needs a capacity check at the point receipts peak, not only at period close. A comfortable closing balance can hide a temporary storage overload. Review the dated receipt sequence with Core Plus’s location context before accepting the intake plan.

THE MERCHMIX DECISION / Core + Core Plus
The ending balance hides an earlier overload
Core’s weekly stock plan needs a capacity check at the point receipts peak, not only at period close.
Independent worked retail example. Operational quantities, policies and outcomes are assumptions, not company data or measured Merchmix results. Financial amounts are in US dollars. Proposed actions remain subject to review.
The ending balance hides an earlier overload
| Measure | Units |
|---|---|
| Immediate peak | 1,300 |
| Period closing | 500 |
The capacity applies to the same physical storage-unit basis.
The capacity applies to the same physical storage-unit basis.
THE KEY IDEA
Check the highest timed stock position as well as the period-end balance before accepting the intake sequence.
Storage has a clock as well as a quantity
A location can finish a month below capacity and still lack safe storage immediately after an earlier delivery. The end balance summarises the period; it does not describe the highest physical stock during it. The relevant capacity must be confirmed for the product’s actual storage format.
Core connects opening stock, intake, sales and closing assumptions. Core Plus supports the location and allocation context. This example adds an operations-owned peak check; it does not assume a native warehouse-space simulation or equate a planogram capacity with every stockroom limit.
The single receipt exceeds the physical limit
An independent location opens Tuesday with six hundred identical storage units and has an operations-confirmed limit of one thousand in that same unit basis. Seven hundred units are due before the next sales occur. The immediate peak would be 1,300, three hundred above the chosen capacity.
The period expects eight hundred unit sales, so opening six hundred plus seven hundred intake less eight hundred sales gives five hundred closing. That ending figure looks comfortable but cannot make the earlier 1,300-unit peak fit.
Test a staged sequence against the same requirement
A proposed sequence receives four hundred first, bringing stock to one thousand. After four hundred sales, six hundred remain. A later three-hundred-unit receipt brings stock to nine hundred; another four hundred sales leave five hundred at period end.
The total intake, sales and closing balance are unchanged. The highest point in this assumed sequence is one thousand rather than 1,300. The alternative works only if both deliveries and the intervening sales occur in the stated order.
THE FIGURES BEHIND THE DECISION
| Case | Total intake | Period sales | Peak units | Closing units |
|---|---|---|---|---|
| Single receipt | 700 | 800 | 1,300 | 500 |
| Staged sequence | 700 | 800 | 1,000 | 500 |
Single peak: 600 + 700 = 1,300. Staged: 600 + 400 = 1,000; less 400 plus 300 = 900; less 400 = 500.
Do not replace a space problem with a service problem
If the later three hundred arrive after customers need them, the proposed schedule may fit storage while failing availability. The forecast’s timing, transport feasibility and receiving workload need their own checks. The example deliberately assumes four hundred sales are served before the second delivery.
A slower first selling interval would leave more stock when that delivery arrives. Define the next review and a supplier communication point before treating the staged plan as dependable. A sequence based on expected sales is not a guaranteed warehouse outcome.
Keep commitment and operating costs separate
At an assumed $20 per unit, the seven-hundred-unit goods commitment stays $14,000. The proposed split is $8,000 of first intake and $6,000 later. It does not create a goods saving or imply the supplier has accepted new delivery terms.
Use Core to compare the dated intake assumptions and Core Plus for location-level stock context. Operations confirms usable capacity and any incremental transport or handling charges. Those costs are not included in the $14,000 goods figure.
Approve the peak and the contingency
The location owner confirms the thousand-unit storage limit, the planner tests the timing between receipts and the buyer obtains supplier acceptance for any revised sequence. Retain the original single-drop plan so the capacity reason remains clear.
This is different from a receiving-throughput restriction: the issue here is how many units are simultaneously stored. A plan should explain both its ending stock and its highest physical requirement.
BEFORE THE NEXT DECISION
- Storage
Location lead; Confirm safe usable capacity
- Demand timing
Planner; Test sales before later receipt
- Delivery
Buyer; Obtain accepted sequence and operating quote
| Signal | Decision owner | Decision to review |
|---|---|---|
| Storage | Location lead | Confirm safe usable capacity |
| Demand timing | Planner | Test sales before later receipt |
| Delivery | Buyer | Obtain accepted sequence and operating quote |
Common questions
Why does five hundred closing stock not prove the plan fits?
The single delivery first raises stock to 1,300 against a one-thousand-unit capacity.
Does staging reduce total goods purchased?
No. Seven hundred units costing $14,000 remain in both cases.
What makes the staged peak one thousand?
Receive four hundred, sell four hundred, then receive three hundred before the final four hundred sales.
Is the revised sequence already accepted?
No. Supplier dates, sales timing, capacity and operating costs require confirmation.
FROM THE ARTICLE TO YOUR OWN RETAIL PLAN
Review the decision.
See the workflow.
Bring your planning questions to a demo, or explore a proof of concept on your own data.