Three Working Days Can Still Miss the Selling Week
Beacon’s confirmed supplier date becomes useful to Core only when its calendar and milestone are clear. A short quoted lead time can span a closure, a dispatch cutoff and a destination receiving restriction. Plan from the first usable stock date rather than adding an unexplained number of days.

THE MERCHMIX DECISION / Beacon + Core
The order misses the supplier’s Friday cutoff
Beacon’s confirmed supplier date becomes useful to Core only when its calendar and milestone are clear.
Independent worked retail example. Operational quantities, policies and outcomes are assumptions, not company data or measured Merchmix results. Financial amounts are in US dollars. Proposed actions remain subject to review.
The order misses the supplier’s Friday cutoff
| Working day | Supplier day |
|---|---|
| First | Monday |
| Second | Thursday |
| Third | Friday |
This is an independent calendar assumption.
This is an independent calendar assumption.
THE KEY IDEA
Use the accepted calendar and milestone sequence to plan useful stock, not a bare lead-time number.
Define the clock before comparing the promise
A lead time may count elapsed days, supplier working days or days from a later event such as approval or payment. Microsoft’s planning guidance distinguishes working-day lead times and the calendars used to calculate dates. That distinction matters before any retailer adds a buffer.
Beacon records supplier acknowledgement and an ex-factory date. Core carries the intake assumption used in MFP/WSSI. Keep those milestones separate: factory readiness is not the same as stock accepted and ready at the selling location.
Count the supplier’s actual open days
An independent order is accepted on Friday after the supplier’s daily cutoff. Its three-working-day production lead time begins on the next open day. The supplier works Monday, is closed Tuesday and Wednesday, then works Thursday and Friday.
Monday is working day one, Thursday day two and Friday day three. The example therefore assumes factory readiness at the end of the following Friday. This is a chosen supplier calendar, not a statement about any country’s public holidays or a standard factory timetable.
Add transport and receiving on their own basis
The route takes two elapsed days from the Friday dispatch, reaching the destination on Sunday. The receiving team is closed Sunday and can make the goods usable at Monday opening, assuming all required checks pass.
The total time from the original Friday cutoff to useful Monday stock is ten calendar days. That number belongs to this exact sequence. A different transport cutoff, inspection delay or receiving calendar would produce a different answer.
THE FIGURES BEHIND THE DECISION
| Event | Chosen timing | Meaning |
|---|---|---|
| Acceptance | Friday after cutoff | Next open day starts clock |
| Workdays | Monday / Thursday / Friday | Three supplier days |
| Arrival | Sunday | Receiving closed |
| Usable | Monday opening | Ten calendar days after acceptance |
Nine full pre-arrival trading days × 10 units = 90 required; 80 held leaves a 10-unit timing gap.
Check the selling days before the useful receipt
The store has eighty usable units on Saturday morning after the order is accepted. It expects ten sales per day across the nine full trading days before the useful Monday receipt. That is ninety units of demand against eighty held, leaving a ten-unit timing gap.
A later two-hundred-unit receipt does not retrospectively serve that earlier demand. Review a feasible bridge or the customer promise separately. This example does not assume a rush order can arrive in time simply because the calculated gap is small.
Make the supplier confirmation intelligible to the planner
Use Beacon’s acknowledged order and ex-factory context to confirm when the supplier clock starts and which closures apply. Operations then confirms transport and receiving. Core’s intake week should use the resulting reviewed useful date, rather than reuse the phrase three days without its basis.
No automatic calendar integration or end-to-end arrival calculation is asserted here. The control is an owned handover: accepted start event, supplier working days, departure, transport and usable receipt. Each owner should be able to explain their part.
Approve a date the business can use
Sourcing confirms the factory date, operations confirms Monday readiness and the planner reviews the ten-unit pre-arrival exposure. Keep the original promise visible so the reason for the later useful date remains clear.
This differs from a supplier whose lead time has become unreliable. Every participant can meet the agreed terms in this example and the retailer can still miss the selling requirement if it plans on the wrong clock.
BEFORE THE NEXT DECISION
- Factory
Sourcing lead; Confirm start event and open days
- Useful receipt
Operations; Confirm route and receiving readiness
- Plan
Planner; Review ten-unit pre-arrival gap
| Signal | Decision owner | Decision to review |
|---|---|---|
| Factory | Sourcing lead | Confirm start event and open days |
| Useful receipt | Operations | Confirm route and receiving readiness |
| Plan | Planner | Review ten-unit pre-arrival gap |
Common questions
Why are Tuesday and Wednesday skipped?
The example assumes the supplier is closed on those days; it is not a public-holiday claim.
Why is stock not usable on Sunday?
The chosen receiving operation is closed then and makes accepted goods usable at Monday opening.
How is the ten-unit gap calculated?
Nine trading days at ten units require ninety, against eighty usable opening units.
Does Beacon calculate all these calendars automatically?
No such capability is assumed. Confirm the supported dates and operational handover.