merchmix

Publish Date :

What Can Retailers Learn from Target's Costly Markdowns and Order Cancellations?

Target’s latest results look back on earlier markdown and purchase order cancellation costs from a stronger margin position. For retailers, the lesson is to connect buying commitments with current demand before the remaining choices become expensive.

TARGET / Q2 2026 / THE COMPARISON MATTERS

Reported gross margin33.7%Includes 3.7 percentage points from tariff refunds
Expansion excluding tariff refunds~100 bpAgainst the prior-year 29.0% rate

An improved margin comparison, including earlier markdown and cancellation costs. The Merchmix example is a separate retailer scenario.

THE RETAIL RESPONSE / MERCHMIX

Demand changed.
What is already committed?

Follow a jacket plan from revised demand into required intake, the existing order and a supplier discussion.

Merchmix buying example. These are not Target operational records.

merchmixcoreUSD / $
PlanningMFP/WSSI & OTB

The revised stock bridge

Separate apparel retailer / one selling-window scenario

Held stock200
Incoming300
Forecast sales250
Projected closing250
Closing objective100 unitsAbove objective150 units
200 held + 300 incoming less 250 forecast sales = 250 closing.

Planning illustration / no amendment or cancellation executed

Keep the existing order in the calculation.

The revised 250-unit demand sits against 200 held and 300 due. Keeping the order gives 250 projected closing units.

THE KEY IDEA

A changed forecast does not change an order. Merchmix Core connects the budget, MFP/WSSI and OTB question; Beacon keeps supplier discussions tied to the right commitment. Confirm the change, then bring it back into the plan.

What Target’s results actually say

Target’s second-quarter 2026 release describes an improvement against the previous year’s elevated markdowns and purchase order cancellation costs. Reported gross margin was 33.7%, including a 3.7 percentage-point benefit from tariff refunds. Excluding those refunds, gross margin expanded by approximately 100 basis points against the prior-year rate of 29.0%.

The release also identifies advertising and non-merchandise sales growth as contributors. Its accompanying earnings overview describes broader progress in the business. The comparison therefore concerns earlier costs, rather than evidence that the same pressure persisted in the current quarter. It does not isolate a dollar amount for markdowns or cancellations, identify the affected orders, or establish a single operational cause.

Source: Target’s official Q2 2026 earnings release.

A markdown and a cancelled order solve different problems

A markdown changes the selling-price assumption for stock a retailer expects to sell. A purchase order amendment changes a supply commitment only when the relevant parties authorise and confirm it. They belong in the same commercial discussion, but their costs and timing differ.

Discounting stock already held cannot remove an incoming order. Equally, asking a supplier to reduce an order does not change the quantity already available in stores. A buyer needs to see the current demand outlook, held stock and open commitments together before choosing a response.

Target’s comparison is a reason to examine that discipline. It is not evidence that Target used a particular planning process, nor that any one system would have prevented the earlier costs.

Start with Core: the budget is a buying assumption

Merchmix connects retail planning with operational decisions. Core is its planning product, bringing budgets, MFP/WSSI and open-to-buy into the merchandise discussion. MFP/WSSI connects the weekly sales, stock and intake plan; open-to-buy, or OTB, assesses the room for further buying against the chosen plan and its existing commitments.

A budget is more useful when the buyer can explain its units, selling prices, costs and time period. If demand changes, updating only the sales target leaves the intake assumption behind. In Core, the next question is how the revised sales profile changes closing stock and the capacity for another commitment.

Keep the value basis consistent. A sales budget at selling value and a purchase order at cost cannot be compared as if they were the same measure. Check the unit position first, then apply the relevant price or cost basis.

Follow one jacket order from forecast to excess exposure

Consider a separate Merchmix apparel example, not Target’s operational records. The retailer holds 200 casual jackets. A confirmed order contains 300 more at $30 each, a $9,000 commitment. The revised selling-window forecast is 250 units, and the planning objective is to close with 100.

Why are only 150 incoming units needed? The retailer needs 250 units for forecast sales plus 100 to meet its closing-stock objective: 350 in total. It already holds 200, so only another 150 are required. The calculation is 250 forecast sales + 100 target closing stock less 200 held = 150 required intake.

However, 300 units are already on order. That is 150 more than the current plan needs. Keeping all 300 would leave 250 at close, rather than the 100-unit objective. The 150-unit commitment gap is therefore excess against this plan, not an approved cancellation, a cash saving or permission to buy another 150. Until an authorised amendment is confirmed, the full order remains included.

At the stated unit cost, that additional 150 represents $4,500 of stock exposure. It is not a cancellation charge, a realised loss or a guaranteed saving. Receipt timing and availability must still support the sales profile; a period-end calculation alone cannot prove the weekly plan is feasible.

Editorial apparel buying scene of a young woman with a blonde pixie haircut checking a sage jacket against an order sheet in an unbranded US workspace

AN APPAREL PLANNING SCENARIO

The demand plan changes. The order still stands.

A separate Merchmix jacket example holds 200 units and forecasts 250 sales, with a 100-unit closing objective. Total stock needed is 350; less the 200 already held, required intake is 150. The existing 300-unit order exceeds that requirement by 150. Keeping the full order leaves 250 at close, or 150 above the objective. At $30 cost, the gap represents $4,500 of exposure, not a confirmed cancellation or saving. These are not Target operational figures.

Illustrative situation, not a customer case study.

Use OTB to identify the commitment gap before another buy

Core’s OTB discussion should begin with the order that already exists. In this simplified unit bridge, required intake of 150 sits against 300 committed. The 150-unit commitment gap means the current assumptions call for a review before more jackets are bought. It does not instruct the supplier to cancel anything.

The buyer can test demand, the closing-stock objective and receipt timing in the MFP/WSSI plan. If one assumption changes, recalculate the effect and keep the decision visible. Avoid treating an unconfirmed quantity reduction as available buying headroom.

This is the important connection between budget and buying: the plan should include the supply the business is still obliged to receive, even when a lower intake would be preferable.

Read the OTB guide

Carry the same order into Beacon

Beacon is Merchmix’s supplier portal. Its Procurement area includes Synced Purchase Orders and order details, giving the supplier-facing discussion a specific reference and set of lines. Match the retailer’s stock order with the supplier view before discussing a change in quantity or arrival date.

In the example, PO-2030 contains small 60, medium 120, large 90 and extra-large 30: 300 jackets in total. The buyer’s proposed retained quantity is 150, split 30, 60, 45 and 15. That would be $4,500 at cost if agreed. It remains a commercial request, not a completed order amendment.

Use the shared order reference to establish what can change, which quantities are affected, the relevant dates and any supplier terms. The illustrated Beacon view shows the existing order and a separate discussion summary; it does not invent a cancellation button or claim a response has been submitted. Until confirmation, the full 300 remain in the planning example.

FROM THE SIGNAL TO THE MERCHMIX DECISION

What to check before the next action

Inventory signals, relevant Merchmix workspaces and decisions to review
What you seeWhere to look in MerchmixThe decision to review
250 closing / 100-unit objectiveCore / MFP/WSSITest the current sales profile, receipt timing and closing-stock objective.
150 required intake / 300 committedCore / OTB and buyingReview the 150-unit commitment gap before placing further jacket orders.
PO-2030 / 300 jackets / $9,000Beacon / Synced Purchase OrdersMatch reference and size lines, then establish whether an amendment is possible.
THE PLANNING CONNECTIONDemand plan + existing commitment + confirmed response

200 held + 300 incoming less 250 forecast sales leaves 250 jackets, against a 100-unit closing objective.

Explore MFP/WSSI

Compare the price decision with the cost of changing supply

For the stock already held, Core can support a markdown planning discussion. Suppose 100 jackets are being assessed at a $60 ticket price or a proposed $48 price, with unit cost held at $30. Selling all 100 would generate $6,000 or $4,800 of revenue, and $3,000 or $1,800 of gross profit before other expenses.

The $1,200 gross-profit difference isolates price for the same assumed quantity. It does not predict that both prices would sell 100 units. A useful decision also tests how much might sell, how quickly, and what remains at the end of the window.

Compare that price scenario with any confirmed supplier amendment terms, using the same horizon and cost basis. The example assigns no cancellation fee because none has been established. Keeping $4,500 of exposure visible is different from claiming $4,500 can be recovered by cancelling an order.

core

Connect budgets, MFP/WSSI and OTB with existing commitments.

Explore core
beacon

Keep supplier collaboration tied to an order reference and its lines.

Explore beacon

Close the loop between the plan and the commitment

Once a supplier response is confirmed and an authorised order change is recorded, update the corresponding intake assumption and recalculate the stock plan. If the request is declined or the timing changes, the plan still needs to reflect what the business will actually receive.

Core supplies the budget, MFP/WSSI and OTB context; Beacon supplies an order-specific place for supplier collaboration. The practical lesson from the earlier costs in Target’s comparison is to connect those decisions while choices remain open, rather than wait until unwanted intake and selling-price pressure must be managed separately.

BEFORE THE NEXT IN-SEASON COMMITMENT

  1. Does the revised sales profile use a consistent unit and value basis?
  2. Which purchase orders remain committed?
  3. What intake would meet the closing-stock objective?
  4. Which supplier terms and dates still need confirmation?
  5. Has the authorised change reached the stock plan?

A CLEARER NEXT STEP

Common questions

Do Target’s 2026 results show the same markdown pressure continuing?

The supplied release describes improved margin compared with the previous year’s elevated markdown and order-cancellation costs. Tariff refunds and advertising and non-merchandise growth also contributed; the article does not attribute the improvement to one inventory action.

Does lower required intake mean an order has been cancelled?

No. It identifies a planning mismatch. In this example the full 300-unit order remains included until an authorised amendment is confirmed.

Is the $4,500 commitment gap a cancellation saving?

No. It is 150 units at $30 cost. Supplier terms, timing and any charges have not been established, so the example does not claim a recoverable saving.

THE ORDER DISCUSSION / BEACON

One reference.
A clear commitment.

Follow PO-2030 from the supplier-facing order list into its size lines. The buyer’s request is shown separately from the existing commitment.

  1. 01
    Match the order

    300 jackets at $30 cost, with the same reference and size breakdown.

  2. 02
    Define the request

    Retain 150 units if agreed, with supplier terms and timing still to confirm.

  3. 03
    Keep the plan honest

    The full 300 remain included until a change is authorised and confirmed.

Explore beacon
beaconby merchmixUSD / $
DashboardProcurementLogisticsFinance
ProcurementSynced Purchase Orders

Synced Purchase Orders

Separate apparel retailer / supplier-facing order check

Order referenceQuantityAt cost
PO-2030Casual Jacket300$9,000
PO-2034Apparel order180$3,600
PO-2038Apparel order240$4,800
Match PO-2030 with the retailer’s stock order.
Ordered300 unitsUnit cost$30

Planning illustration / no amendment or cancellation executed

Start with a matched order reference.

Beacon’s Synced Purchase Orders provides the supplier-facing reference. PO-2030 remains a 300-unit, $9,000 commitment.

Separate Merchmix order scenario. The discussion summary is explanatory; no supplier response, cancellation or amendment is submitted.

FROM BUYING ASSUMPTION TO CONFIRMED COMMITMENT

Read the demand.
Know the commitment.

A changed forecast does not change an order. Merchmix Core connects the budget, MFP/WSSI and OTB question; Beacon keeps supplier discussions tied to the right commitment. Confirm the change, then bring it back into the plan.

See merchmix in action Explore core